Home | News › The difference in driving speed between conventional hammering and a Vibratory Hammer - Saving significant installation time for OWF Monopiles

The difference in driving speed between conventional hammering and a Vibratory Hammer - Saving significant installation time for OWF Monopiles

Increasing installation efficiency is a key component of LCOE reduction for the offshore wind industry. By reducing the installation time for key components such as Monopiles, significant savings on vessel hire can be made.

The 2018 average installation rate, where the vessel installed both monopiles and transition pieces, is 2.27 Days per Foundation (DpF). When using Vibratory Technology the DpF can drastically been reduced.

These video's were made during a comparison test in Germany and what you see is the actual speed. For the test we used the exact same Monopiles and exact same soil conditions. Besides the installation speed advantage, vibrating technology is less harmful to the sub-sea environment (Marine mammals, fish and other sealife) because of the much lower noise level during installation.






Share this page:

Support / Advice

Find out if Piling & Vibro Equipment can assist you.

T: +31 184 410 333
(E) offshore@pve-holland.com

Piling & Vibro Equipment

  • Smart vibro solution
  • Time saving foundation equipment
  • More accuarate pile positionning
  • Minimizing damage to marine life

Request for more information about The difference in driving speed between conventional hammering and a Vibratory Hammer - Saving significant installation time for OWF Monopiles

PVE A WORLDWIDE SOLUTION
© 2024 PVE Piling & Vibro Equipment
Webdesign & Development: HPU internet services